Not yet a registered school. We cannot accept enrolments. Target opening Term 1, 2030. Where things stand

Progress

Every approval, and where it actually stands.

This page is updated whenever something changes. If it has not changed in a while, that is because nothing has — and we would rather you saw that than saw nothing.

Last updated October 2026

  1. 2024 · Complete

    Company incorporated and registered as a charity

    Dawn Knowledge Institute Limited registered on 2 October 2024 and registered with the ACNC from the same date.

  2. 2024 · Complete

    Site identified at Bennett Springs

    375 Marshall Road chosen as the proposed campus.

  3. 2025 · Complete

    Concept design and staged plan

    Site layout, staging and indicative building design.

  4. 2026–27 · In progress

    Governance and planning

    Strengthening the governing body — constitution, membership, board, school policies and financial planning — to the standard the Department of Education requires.

  5. Open now

    Registering family interest

    Every family who registers strengthens the application. Information evenings begin in 2027.

  6. Mid-2028 · Planned

    Application for advance determination

    To the Minister for Education, at least 18 months before opening. The application is publicly consulted on before a decision is made.

  7. 2029 · Planned

    Development approval and Stage 1 construction

    Approval from the City of Swan, then building the first stage of the campus.

  8. By 1 July 2029 · Planned

    Application for initial registration

    To the Director General of the Department of Education, at least six months before the registration date, assessed against the registration standards.

  9. Late 2029 · Planned

    Registration decision, then enrolments open

    Enrolments open only once registration is granted. Registered families are contacted first.

  10. Term 1, 2030 · Target

    Springs College opens

    Kindergarten to Year 2, adding a year level each year.

Why the dates are what they are

Western Australia runs a two-stage process under the School Education Act 1999. An application for advance determination must be lodged at least 18 months before a school opens, and an application for initial registration at least six months before the registration date. Those lead times, not our impatience, set the opening year.


Approvals

Approvals required and their status
ApprovalGranted byStatusDate or target
Charity registrationAustralian Charities and Not-for-profits CommissionGranted2 October 2024
Income tax exemption and GST concessionAustralian Taxation OfficeGranted2 October 2024
Deductible gift recipient endorsement (school building fund)Australian Taxation OfficeNot yet applied forApplication planned for 2027
Advance determinationMinister for EducationNot yet applied forApplication planned for mid-2028
Development approvalCity of SwanNot yet applied forPlanned for 2028–29
Initial registrationDirector General, Department of EducationNot yet applied forApplication by 1 July 2029

Target dates are our plan and can move. Each approval is decided by the body named, not by us.